ޕްރޮޖެކްޓް Project:
|
Consultancy Service to assessing groundwater resources and design of aquifer recharge systems in selected 17 islands of Maldives (GCF Project)
|
|
ތާރީހް Issued Date: |
17th December 2020 |
|
ބިޑް ހުށަހަޅަންޖެހޭ ތާރީހް Bid Submission Date
|
07th January 2021 10:00hrs |
Please include this addendum when submitting the bid. ބިޑް ހުށަހަޅުއްވާއިރު މި ގަނޑުވެސް ޑޮކިއުމަންޓާއި އެކު ހުށަހެޅުއްވަން ޖެހިވަޑައިގަންނަވާނެއެވެ.
1) Page 14, 5.5 Submission Receipts and opening of proposals
The Wordings for Submission receipts and Opening of proposal should be revised as below.
|
Submission, Receipt, and Opening of Proposals
|
The Proposal submission address is:
GCF Project Management Unit Water and Sanitation Department Ministry of Environment, Green Building, Handhuvaree Hingun, Maafannu, Male’, 20392, Republic of Maldives.
The proposals are expected to be submitted to the address on local time 1000hrs 07th January 2021. Only bids submitted at this time will be eligible to proceed to evaluation and Late bids will be rejected.
Interested parties should register their interest by email no later than Before 1200hrs on 22nd December 2020. And send clarifications by 22nd December 2020. Only those parties who register their interest will be allowed to participate in the bid.
Proposal of additional or alternative conditions to RFP is not allowable |
2) Page 48, 5. Duration and Payment Schedule and page 54, 2. Reporting Requirements
The Wordings for duration and payment schedule and reporting requirement should be revised as below.
5. Duration and Payment Schedule
|
Activity / Deliverable |
Due date and remarks |
|
Inception Report with a detailed methodology and consultancy implementation plan. This will be based on prior consultation with the PMU and other key stakeholders |
30 Calendar days from contract signature, upon client review and approval |
|
Baseline assessment report with catchment and aquifer characterization Report and presentation |
150 Calendar days from contract signature, upon client review and approval |
|
Feasibility and Concept Design Report and presentation |
210 Calendar days from contract signature, upon client review and approval |
|
Video clip |
240 Calendar days from contract signature, upon client review and approval |
|
Detailed Design Report and presentation |
270 Calendar days from contract signature, upon client review and approval |
|
Tender documents |
300 Calendar days from contract signature, upon client review and approval |
3) Clarifications:
Please find the answers to clarifications attached with this amendment.