Design, Build and Turnkey Project to Establish a Central Powerhouse for GDH. Madaveli and GDH. Hoadehdhoo

Reference No: FNK-I/IUL/2020/066

Design, Build and Turnkey Project to Establish a Central Powerhouse for GDH. Madaveli and GDH. Hoadehdhoo

 

Fenaka Corporation Limited requests quotation from interested local and foreign companies to design, build and turnkey project to establish a Central Powerhouse for Gdh. Madaveli and Gdh. Hoadehdhoo as per information provided in the bid document and in pre-bid session.

  • All bids should be accompanied with a bid security of USD 10,000.00 (Ten Thousand US Dollars).
  • Bid security should be:

-          Original bank guarantee letter (or)

-          Bank guaranteed and stamped cheque (or)

-          An insurance policy from Maldives Monetary Authority registered insurance company.

  • Bid security must be submitted in the name of the bidder.
  • Bid security should be valid for 20 (twenty) additional days beyond the validity of the quotation.
  • Bid should be valid for a period of 60 (sixty) days from the date of bid opening.

 

Date

Time

Bid Registration

03rd – 05th March 2020

0900hrs – 1400hrs

Information Session

05th March 2020

1300hrs

Inquiries Deadline (via e-mail)

22nd March 2020

1400hrs

Bid Opening

25th March 2020

1000hrs

 

There is a pre-bid information session for interested parties on 05th March 2020, Thursday 1300hrs (Maldivian time) at Fenaka Corporation Head Office (7th Floor, Ports Complex Building). Interested bidders shall also register at Fenaka Corporation Head Office as mentioned above and late registration is not accepted.

Bids shall be opened on 25th March 2020 at 1000hrs Maldivian time, in the presence of the bidders and any late bids will be rejected.

Important Note:

Please note companies can either register and/or attend pre-bid meeting to be eligible to participate in this tender. Also, it is in Fenaka Corporation Limited’s discretion to cancel this bid invitation at any time. All inquiries shall be emailed to [email protected]

 

 

 

 

01 March 2020