Addendum 1 - Upgrading of Waste and Resource Management Center (WRMC) in Goidhoo, Baa Atoll

       Reference No:  (IUL)438-WMPC/438/2023/211

Addendum 1 -  Upgrading of  Waste and Resource Management Center (WRMC) in Goidhoo, Baa Atoll

 

Reference to the below invitations published by the Ministry of Environment, Climate Change and Technology (MoECCT) under financing from The World bank to upgrade  Waste and Resource Management centers in Goidhoo Baa Atoll.

For the information of the registered bidders, please be informed that evaluation criteria in the tender document revised as follows:  

9. Eligibility and Qulification Criteria

Must have at least MVR 346,950.00 as average bank balance of the last 3 months.

Alternatively, bidder may submit financial statements or audited balance sheets having an average annual turnover of MVR 346,950.00 during the last Three (3) years (2019, 2020, 2021).

 

9.f